Hi Guys!
need your urgent help please!
I have my schedule prepared in P3. I prepared the detailed schedule in P6 by importing it. After completing the detailed schedule, I exported it back to P3 version.
As I open the P3 file of my detailed schedule, the logic/relationships is no longer working. Even if you change a relationship, it does not recalculate.
Please help me asap.
Thanks,
Ariel
got answer to my question...by re-selecting the Project Start date at Project Overview then re-scheduling(not shortcut/F9) re-specifying the data date...this is because P6 has time in calendar/consider time in the calculation i guess.