Finish date is not same as Early finish or late finish

K
kp rao 👤 Member for 14 years 10 months

Hi,

I need urgent help.

I am using p6v7.I never faced this problem.

I have an activity with type WBS summary.In this we have Project start (15 sep-2011)and project finish(15-sep-2014).

Early finish is 15-sep-2014.Late finish is 15-sep-2014.But the Finish col showing 11 sep 2014.

Can I adjust it or to show it equal to Early finish.

Urgent help please.

kp