project finish date

S
Sunil Babu 👤 Member for 15 years 7 months

Hi friends,

I have finish constraint for my project eg: must finish on or before

12-dec-2012 and I scheduled my project but the project showing the

finish date as 16-feb 2013 why it is happening like this...

your expert advice highly appreciated..

Regards.

Sunil

G
Gary Whitehead 👤 Member for 17 years 3 months

...but if the date was showing 16th feb with the fniish on or before constraint, this is becuase your schedule is telling you it is impossible to finish by 12th dec.

Making it a mandatory constraint will make the end date change, but it doesn't mean you will achieve that end date.

 

Really, you're just hiding the problem, rather than adressing it.

This is why I do not like mandatory constraints.

D
Daniel Limson 👤 Member for 24 years 8 months

Hi Sunil,

If you dont want your end date to move, used "Mandatory Finish"

Cheers,

Daniel

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts