Hi friends,
I have finish constraint for my project eg: must finish on or before
12-dec-2012 and I scheduled my project but the project showing the
finish date as 16-feb 2013 why it is happening like this...
your expert advice highly appreciated..
Regards.
Sunil
...but if the date was showing 16th feb with the fniish on or before constraint, this is becuase your schedule is telling you it is impossible to finish by 12th dec.
Making it a mandatory constraint will make the end date change, but it doesn't mean you will achieve that end date.
Really, you're just hiding the problem, rather than adressing it.
This is why I do not like mandatory constraints.
Hi Limson,
Thanks for your reply
Regards
Sunil
Hi Sunil,
If you dont want your end date to move, used "Mandatory Finish"
Cheers,
Daniel