project finish date

S
Sunil Babu 👤 Member for 15 years 6 months

Hi friends,

I have finish constraint for my project eg: must finish on or before

12-dec-2012 and I scheduled my project but the project showing the

finish date as 16-feb 2013 why it is happening like this...

your expert advice highly appreciated..

Regards.

Sunil

G
Gary Whitehead 👤 Member for 17 years 2 months

...but if the date was showing 16th feb with the fniish on or before constraint, this is becuase your schedule is telling you it is impossible to finish by 12th dec.

Making it a mandatory constraint will make the end date change, but it doesn't mean you will achieve that end date.

 

Really, you're just hiding the problem, rather than adressing it.

This is why I do not like mandatory constraints.

D
Daniel Limson 👤 Member for 24 years 7 months

Hi Sunil,

If you dont want your end date to move, used "Mandatory Finish"

Cheers,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts