GOood morning ,
This is the question
I changed the data date and pressed F9 =>the remaining duration didn't changed but at complete duration increased
I want that remaining duration change automatically so the remaining units in ressources increase and the formula
AT COMPLETE DURATION =Actual duration+Remaining duration still correct
thanks
I would like to know how to copy the budgeted units activity wise on a weekly timescale in P6
Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.
Please let me know if this is not what you meant. Thanks!
Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.
Please let me know if this is not what you meant. Thanks!
Hi Somasundaram K,
I jump of your proposal and I would be interested to get any feedback.
To update my project, I am filling "Expected Finish" field (only activity started).
First consequence is to get FF=0 on this activty.
Is there any other consequence in scheduling ?
Is it a good practice to fill this field instead of modifying directly finish date ?
regards
Schedule using Expected Finish date field. That should solve your problem. Thanks!