I am assuming that you presently have a Project with certain activities updated. What you need to do is set this present scheduke with its Actual Dates as a Baseline.
You do not need to assign this baseline to any Project. Simply restore this Baseline by clicking on the "Restore" tab in the "Maintain Baseline" box and you have a Project available in your database that has the Actual Dates now showing as your "Start" and "Finnish" dates.
Save this as a baseline again and assign it to have your "Actual Dates" now show up as "Baseline Dates" for the Project to which you assigned the baseline.
From my own experience, lets say you have Actual Dates for Activity A as Actual Start 01/01/2012 and Actual Finnish as 01/10/2012.
Activity B is a succesor to Activity A and is scheduled to start the very next day.
But when you follow the above procedure to get the Actual Dates of Activity A as Baselines Dates, you will notice that Activity B may be scheduled to start after a days gap and not the very next day as Planned in the program iin which you had upadated Actual Dates for Activity A. To resolve this I had reassigned a new Calender to the Programm and Scheduled it which realigned the Activities to start the very next day. If you want to use the same Calendar, simply create a similar new calendar and then reassign it.
I hope you find this usefull and is what you were looking for.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi,
Here's one simple method:
1. Open current Program. Export as .xer
2. Open Baseline Program.
3. Import the .xer current program. Select Update. Select the Baseline Program to update.
Hope this will help.
Hi Amro,
I am assuming that you presently have a Project with certain activities updated. What you need to do is set this present scheduke with its Actual Dates as a Baseline.
You do not need to assign this baseline to any Project. Simply restore this Baseline by clicking on the "Restore" tab in the "Maintain Baseline" box and you have a Project available in your database that has the Actual Dates now showing as your "Start" and "Finnish" dates.
Save this as a baseline again and assign it to have your "Actual Dates" now show up as "Baseline Dates" for the Project to which you assigned the baseline.
From my own experience, lets say you have Actual Dates for Activity A as Actual Start 01/01/2012 and Actual Finnish as 01/10/2012.
Activity B is a succesor to Activity A and is scheduled to start the very next day.
But when you follow the above procedure to get the Actual Dates of Activity A as Baselines Dates, you will notice that Activity B may be scheduled to start after a days gap and not the very next day as Planned in the program iin which you had upadated Actual Dates for Activity A. To resolve this I had reassigned a new Calender to the Programm and Scheduled it which realigned the Activities to start the very next day. If you want to use the same Calendar, simply create a similar new calendar and then reassign it.
I hope you find this usefull and is what you were looking for.
Regards,
Abdullah Merchant.
Hi Ahmed,
You should create a baseline of your current schedule by following path:
Tool > Maintain Baseline.....
After assign it to your Project our primary baseline in order to have it visible on your layout,
regards