Delay Analysis using Impacted As Planned Method

Hi,

If you can, please give me some advice regarding this Delay Analysis Problem.  I used “Impacted As Planned” method to analyses delays.

For the very first delay Event, I just took the Baseline & Impact the Delay into that. Now, my Problem is for the Next Delay event, should I use the Baseline or Already Impacted Programme to demonstrate the Delay Analysis.

Thank You

M
Mike Testro 👤 Member for 20 years 7 months

Hi Prageeth

You should impact your delay events in strict chronological order of date of impact using the same chart in a rolling sequence.

The date of impact is the last date that the impacted activity could start after the event has run its course.

Bear in mind that the Impacted As Planned method as described in the SCL protocol 2002 is not to be used for Forensic Delay Analysis but only for Work in Progress.

Best regards

Mike Testro

Featured Partner

Top Posters

Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts