I want to estimate MANPOWER that is required to complete a project: I have a plan with thousands of activities, duration, start and end dates but don't know how many resources do i require to complete it.
So how can i estimate it in Primavera 6 in Top Down Estimate? Please explain and i would really appreciate the snapshot/video tutorial for this.
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Wed, 2007-06-13 09:04
You open your project with the view "WBS". You click onto the detail tab "Budget log".
The first level is the project itself, the others are the different levels of the WBS. Now you enter the appropriate figures.
Later, after you planned your activities with workload*price/unit and the expenses youll be able to compare on any level if your plan corresponds to your budget.
Reards
Dieter
Member for
21 years 9 months
Member for21 years9 months
Submitted by Emmanuel Udo on Tue, 2007-06-12 12:35
Member for
15 years 8 monthsHi,I write an article
Hi,
I write an article regarding How does “Top Down Estimation” in Primavera P6 work?
If you're interested, kindly read it here https://doduykhuong.wordpress.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/
Cheer
Member for
13 years 10 monthsI want to estimate MANPOWER
I want to estimate MANPOWER that is required to complete a project: I have a plan with thousands of activities, duration, start and end dates but don't know how many resources do i require to complete it.
So how can i estimate it in Primavera 6 in Top Down Estimate? Please explain and i would really appreciate the snapshot/video tutorial for this.
Member for
18 years 9 monthsRE: Top Down Estimating in P3e
Hi Emmanuel,
You open your project with the view "WBS". You click onto the detail tab "Budget log".
The first level is the project itself, the others are the different levels of the WBS. Now you enter the appropriate figures.
Later, after you planned your activities with workload*price/unit and the expenses youll be able to compare on any level if your plan corresponds to your budget.
Reards
Dieter
Member for
21 years 9 monthsRE: Top Down Estimating in P3e
I want to estimate money at both EPS and WBS levels.
Kind regards.
Emmanuel
Member for
19 years 1 monthRE: Top Down Estimating in P3e
Hello Emannuel,
I would try to help you, but I need to know what you are
planning to do?
Do you want to make a "Top Down Estimate" in order to
compare your estimation with your schedule?
Which values do you want to estimate? (money, people, material? Anything else then money will be very difficult.)
Would you estimate the availiable money on the project and WBS-Level or also on EPS-Level?
Would you estimate the money in one block per EPS / Project / WBS or also by month?
Kind regards
Peter