Hi,
I write an article regarding How does “Top Down Estimation” in Primavera P6 work?
If you're interested, kindly read it here https://doduykhuong.wordpress.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/
Cheer
I want to estimate MANPOWER that is required to complete a project: I have a plan with thousands of activities, duration, start and end dates but don't know how many resources do i require to complete it.
So how can i estimate it in Primavera 6 in Top Down Estimate? Please explain and i would really appreciate the snapshot/video tutorial for this.
Hi Emmanuel,
You open your project with the view "WBS". You click onto the detail tab "Budget log".
The first level is the project itself, the others are the different levels of the WBS. Now you enter the appropriate figures.
Later, after you planned your activities with workload*price/unit and the expenses youll be able to compare on any level if your plan corresponds to your budget.
Reards
Dieter
I want to estimate money at both EPS and WBS levels.
Kind regards.
Emmanuel
Hello Emannuel,
I would try to help you, but I need to know what you are
planning to do?
Do you want to make a "Top Down Estimate" in order to
compare your estimation with your schedule?
Which values do you want to estimate? (money, people, material? Anything else then money will be very difficult.)
Would you estimate the availiable money on the project and WBS-Level or also on EPS-Level?
Would you estimate the money in one block per EPS / Project / WBS or also by month?
Kind regards
Peter