I have been using four week look ahead schedules for a long time in my construction and energy industry projects to recognize what work will to be done in the next four weeks. You should define two parameters in the filter window which are activity start dates and activity status. You can read this article to create your four week look a head filter quickly.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I have been using four week look ahead schedules for a long time in my construction and energy industry projects to recognize what work will to be done in the next four weeks. You should define two parameters in the filter window which are activity start dates and activity status. You can read this article to create your four week look a head filter quickly.
Hello Raul,
There should be a default filter for this 4week look ahead. But if there isnt, details on how to add a filter is below:
1. click on filter
2. click on add or modify
3. you should see a window with 5 columns
Column 1 - Display all rows = put "where"
Column 2 - Parameter = "Start"
Column 3 - Is = "is within range of"
Column 4 - Value = "DD"
Column 5 - High Value = "DD+4W"
4. Then you need to add another filter within that same filter (this will give you activities in progress).
5. the answers to add for the 5 columns are below:
Column 1 = Or
Column 2 = Activity Status
Column 3 = Equals
Column 4 = In Progress
Column 5 = leave this column blank
Hope this helps
Regards
Hilal Hallani