Yes you are right. I can calculate and store these planned figures for each activity in a custome data coulmn.
My problem is that P3 can not caluclate it for overall project.(a total %) If you summerize, it shows you all these values added (for example 2400!) I want a figure between 1-100%.
you can’t find the direct variable of planned % in P3 but you can use global change to represent your calculation and that can be stored in a custom data variable.
Thanks for your reply but anyhow if there was any built-in column as Planned %Complete my problem would be solved with your proposed method.
The point is that P3 is not calculating planned progress. It says only planned value (BCWS) which is useless for my client. They are concerned about the progress not value. Could you please inform me where I can find planned %complete coulmn in accordance with my target file? Thanks
you can use P3->Tools->Option->summarization option to choose the required parameter and use Organisation option and choose "Project" in the group by area and then in the total option to choose "Top" to show overall progress.
(Note: If you set your proper target schedule in the target area, you can display both planned and actual progress as explained in the above manner)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi it is very easy.
1) Make a copy of your schedule.
2) Update this schedule automatic (Crtl f9)
3) Assign it as a Target (2)
4) Ask column Target (2) Percent Complete
5) Even if you summarize now it will be correct
So evry week you must just remember to update Progress in the Target 2 Schedule.
Cheers
Yes you are right. I can calculate and store these planned figures for each activity in a custome data coulmn.
My problem is that P3 can not caluclate it for overall project.(a total %) If you summerize, it shows you all these values added (for example 2400!) I want a figure between 1-100%.
you can’t find the direct variable of planned % in P3 but you can use global change to represent your calculation and that can be stored in a custom data variable.
HTH
[Duplicate posting deleted by Moderators.]
Thanks for your reply but anyhow if there was any built-in column as Planned %Complete my problem would be solved with your proposed method.
The point is that P3 is not calculating planned progress. It says only planned value (BCWS) which is useless for my client. They are concerned about the progress not value. Could you please inform me where I can find planned %complete coulmn in accordance with my target file? Thanks
you can use P3->Tools->Option->summarization option to choose the required parameter and use Organisation option and choose "Project" in the group by area and then in the total option to choose "Top" to show overall progress.
(Note: If you set your proper target schedule in the target area, you can display both planned and actual progress as explained in the above manner)