In Scotland we say "tight" not just in regard to production rates! Maybe your Owner has deep pockets and short arms!
Anyway, I hope it all works out for you.
I would be tempted to chat to your Client in a very informal way, and revisit the issue from time to time throughout the contract period. Dont let the matter drop. Hopefully he will appreciate your efforts and as his trust in you increases I am sure that he will soften his hardline approach! ;-)
I believe that the owners estimate of the required number of days was incorrect. After reviewing the Contractor CPS it appears that while "tight" the expected production rates, and sequence of events is reasonable. Therefore I think the owner must ultimately take responsibility for providing improper documentation to me at the time of tender. Much like a contractor has the right to claim on a major underrun of an item I think I have the right to claim on a major underrun since it is the hours and days that are my only item.
We shall see how it all turns out. Thanks again!
This owner is well known for being ......shall be say...."frugal"?
I can sympathise with you; what surprises me is the extent of the reduction in the anticipated contract period by 44%. Was the Owner’s original estimate of the contract period so incompetent?
He must have saved something out of his overall budget for the construction works if the Contractor can knock so much off the RFQ time frame (or, in the alternative, the Contractor’s planning is itself so incompetent that he has underestimated the work involved and you will be required to stay on longer to sort out the inevitable claims at the end of the project!!)
I would have thought that you could negotiate some form of uplift to your rates to take account of your fixed overheads in particular that now require to be met out of substantially reduced income.
If your daily rate is stated as being tied to or based specifically on a period of 386 days, then I think that you have a reasonable case for seeking an uplift in your rates.
Certainly – and as I said earlier – if you need to accelerate your work particularly in having to turn deliverables around in a shorter period, then some form of additional acceleration costs may well be applicable. I don’t quite understand the Owner’s position that you would get paid if the contract went over 386 days; would he expect you to otherwise work for free if the contract overran?
You are right; a Contract is a Contract, but the world is full of aggrieved consultants and engineers who have been screwed by their Clients – it isn’t just Contractors that get the rough end of the stick!!
At the time of bidding my part of this project, the Owner advertised 386 days. I am responsible for project management on the part of the owner.
The contractor carrying out the work submitted a schedule showing that their intention was to only use 216 day.
Since I bid my part of the project long before the contractor did, I had no way of knowing what timeframe they would actually want to complete the work in and as such had to go with the 386 days listed in my contract and as estimated by the owner. Now, since the contractor is basing his schedule on 216 days the owners position is that I will only be paid for the actual time the contractor takes to do the work.
All of the same deliverables will be required in this same (now shortened) time period so there is little doubt that there will be acceleration on my part. Loss of profit etc..
The owners position is that a daily-rate contract means that I am guarateed to be paid if the contract goes over the original 386 days so I have no entitlement if it goes under. I dont think this is correct. A contract is a contract....isnt it?
While it ultimately depends on the jurisdiction of your Contract (and more able minds than mine can comment on Canadian law, if that is the appropriate one), is this not in some way related to an increase to accelerate, or in the alternative, a Change/Variation Order.
You do not explain WHY the Contract period was reduced by 44 % from 386 to 216 days. Was it because of a reduction in workscope? – If so, then you may be able to claim for loss of anticipated profit and recovery of overheads, based on a “negative” Change Order
If the reduction was not due to a reduction in workscope, which means that the same nature and extent of work has to be carried out in a lesser period, this could be a claim for acceleration. Do you need to engage more staff to ensure that the work is completed within the reduced period?
Or is it a political move (the Client has a mate who can do it cheaper than you!?!)
Notwithstanding the Client’s view that you have no recourse on the basis of a daily rate Contract, if you can demonstrate that you have been prevented from gaining other worthwhile work elsewhere as a result of this substantial change, then you may have some entitlement. In addition, seriously consider the chances of ever working for this same Client in the future; if there is any chance, you may just have to bite the bullet and move on!!
Since this is a daily-rate contract is it implied by law that the owner is responsible for any overrun of days but reaps the entire benefit of any underrun (ie under budget)?
Does the estimated duration by the owner for a certain number of days entitle the bidder to a guarantee (reasonably) that those number of days offered in the tender can be expected or is it simply a bidder beware situation?
In my opinion if your contract calls for 386 days then it is a breach of contract by your client as considerable scope of work has been ommitted from the original contract and you can claim for your damages.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Jaco,
Most probably not Jaco.
Regards,
Don
Hi Don
I was just wondering if the contract ended up being 450 days would the "owner" have recieved (Expected) a credit for the fixed fees.
Cheers
Don,
In Scotland we say "tight" not just in regard to production rates! Maybe your Owner has deep pockets and short arms!
Anyway, I hope it all works out for you.
I would be tempted to chat to your Client in a very informal way, and revisit the issue from time to time throughout the contract period. Dont let the matter drop. Hopefully he will appreciate your efforts and as his trust in you increases I am sure that he will soften his hardline approach! ;-)
Good luck
Stuart
Thanks for your thoughts.
I believe that the owners estimate of the required number of days was incorrect. After reviewing the Contractor CPS it appears that while "tight" the expected production rates, and sequence of events is reasonable. Therefore I think the owner must ultimately take responsibility for providing improper documentation to me at the time of tender. Much like a contractor has the right to claim on a major underrun of an item I think I have the right to claim on a major underrun since it is the hours and days that are my only item.
We shall see how it all turns out. Thanks again!
This owner is well known for being ......shall be say...."frugal"?
Regards
Don
Don,
I can sympathise with you; what surprises me is the extent of the reduction in the anticipated contract period by 44%. Was the Owner’s original estimate of the contract period so incompetent?
He must have saved something out of his overall budget for the construction works if the Contractor can knock so much off the RFQ time frame (or, in the alternative, the Contractor’s planning is itself so incompetent that he has underestimated the work involved and you will be required to stay on longer to sort out the inevitable claims at the end of the project!!)
I would have thought that you could negotiate some form of uplift to your rates to take account of your fixed overheads in particular that now require to be met out of substantially reduced income.
If your daily rate is stated as being tied to or based specifically on a period of 386 days, then I think that you have a reasonable case for seeking an uplift in your rates.
Certainly – and as I said earlier – if you need to accelerate your work particularly in having to turn deliverables around in a shorter period, then some form of additional acceleration costs may well be applicable. I don’t quite understand the Owner’s position that you would get paid if the contract went over 386 days; would he expect you to otherwise work for free if the contract overran?
You are right; a Contract is a Contract, but the world is full of aggrieved consultants and engineers who have been screwed by their Clients – it isn’t just Contractors that get the rough end of the stick!!
Cheers,
Stuart
www.rosmartin.com
Thanks Stuart,
At the time of bidding my part of this project, the Owner advertised 386 days. I am responsible for project management on the part of the owner.
The contractor carrying out the work submitted a schedule showing that their intention was to only use 216 day.
Since I bid my part of the project long before the contractor did, I had no way of knowing what timeframe they would actually want to complete the work in and as such had to go with the 386 days listed in my contract and as estimated by the owner. Now, since the contractor is basing his schedule on 216 days the owners position is that I will only be paid for the actual time the contractor takes to do the work.
All of the same deliverables will be required in this same (now shortened) time period so there is little doubt that there will be acceleration on my part. Loss of profit etc..
The owners position is that a daily-rate contract means that I am guarateed to be paid if the contract goes over the original 386 days so I have no entitlement if it goes under. I dont think this is correct. A contract is a contract....isnt it?
Don,
While it ultimately depends on the jurisdiction of your Contract (and more able minds than mine can comment on Canadian law, if that is the appropriate one), is this not in some way related to an increase to accelerate, or in the alternative, a Change/Variation Order.
You do not explain WHY the Contract period was reduced by 44 % from 386 to 216 days. Was it because of a reduction in workscope? – If so, then you may be able to claim for loss of anticipated profit and recovery of overheads, based on a “negative” Change Order
If the reduction was not due to a reduction in workscope, which means that the same nature and extent of work has to be carried out in a lesser period, this could be a claim for acceleration. Do you need to engage more staff to ensure that the work is completed within the reduced period?
Or is it a political move (the Client has a mate who can do it cheaper than you!?!)
Notwithstanding the Client’s view that you have no recourse on the basis of a daily rate Contract, if you can demonstrate that you have been prevented from gaining other worthwhile work elsewhere as a result of this substantial change, then you may have some entitlement. In addition, seriously consider the chances of ever working for this same Client in the future; if there is any chance, you may just have to bite the bullet and move on!!
Stuart
www.rosmartin.com
Thanks for the reply Dinesh,
Since this is a daily-rate contract is it implied by law that the owner is responsible for any overrun of days but reaps the entire benefit of any underrun (ie under budget)?
Does the estimated duration by the owner for a certain number of days entitle the bidder to a guarantee (reasonably) that those number of days offered in the tender can be expected or is it simply a bidder beware situation?
Hi Don,
In my opinion if your contract calls for 386 days then it is a breach of contract by your client as considerable scope of work has been ommitted from the original contract and you can claim for your damages.
Regards
Dinesh