Hi all P6 Users,
Can any one Explain me that how P6 Calculates Origional Duration and Actual Duration.I was applying a Threshold "Duration % Of rigional (%)" and you must know that
Duration % of Origional (% )= Actual Duration / Original Duration * 100
Now I Am not having a clear understanding that how P6 Calculates Actual Duration and Origional Duration Values.
Please Clear This Concept.
Thanks in Advance.
Arian
Hi Aries,
Can you tell me if you want formuale for Duration % Complete? Cause Original duration is a punched in value and Actual Duration is etiher punched in or Calculated depending on whether you entererd Remaining Duration or Actual % Complete.
Regards
Amit
Check out my blog on Primavera at http://www.primaverablog.in
Hi Aries Arian
Check this link
http://www.scribd.com/doc/55614585/Project-Managment-Application-of-Primavera-p6
Cheer's
Shahul
Please Give Response.