Hi..Friends , Can any one guide me to solve the problem
The totals appearing in the summary bands are incorrcet.
Regards,
Naga Bhushan
Hi..Friends , Can any one guide me to solve the problem
The totals appearing in the summary bands are incorrcet.
Regards,
Naga Bhushan
Naga,
What totals are incorrect? Budgeted Manhours? Remaining Manhours? Duration?
Do you have any filters applied?
P6 has some issues when subtotaling durations when there is lag involved (especially the taboo negative lag), or multiple flow paths.
Please provide a more detailed discription of your issue.
Scott
Hi Nagha,
Can you mention the Example here that How The Summary Bar is Showing the Wrong total??? It Can't be.I think you are confused with the Project Durations and the RelationShips.The Summary Bar calculates the total by Considering the Lag (+ve & -ve).Check it again.
Regards.
hi shahul,
Can you check this thread "Threshold urgent"..its unanswered and i am also Interested to Know the Solution
Regards,
Hi Naga Bhushan Jangam
It happens in P6 ,try by scheduling once again
Cheers
Shahul