Totals in Summary bands error

Hi..Friends , Can any one guide me to solve the problem

The totals appearing in the summary bands are incorrcet.

Regards,

Naga Bhushan

S
Scott McComb 👤 Member for 14 years 7 months

Naga,

 

What totals are incorrect?  Budgeted Manhours?  Remaining Manhours? Duration? 

 

Do you have any filters applied?

 

P6 has some issues when subtotaling durations when there is lag  involved (especially the taboo negative lag), or multiple flow paths.

 

Please provide a more detailed discription of your issue.

 

Scott

A
AB Timo 👤 Member for 14 years 11 months

Hi Nagha,

Can you mention the Example here that How The Summary Bar is Showing the Wrong total??? It Can't be.I think you are confused with the Project Durations and the RelationShips.The Summary Bar calculates the total by Considering the Lag (+ve & -ve).Check it again.

 

Regards.

A
AB Timo 👤 Member for 14 years 11 months

hi shahul,

Can you check this thread "Threshold urgent"..its unanswered and i am also Interested to Know the Solution

 

Regards,

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts