Need Help on Resource Usage Profile

I need help...

Why my "Display Activities for selected..." function at bottom left pane in the Resource Usage Profile view is greyed out? I cant mark/click neither "Time Period" nor "Resource" options.

N
Nik Muhammad 👤 Member for 14 years 7 months

It works! I have to uncheck "show all project" in the right bottom panel. Thanx a lot...

M
Mohammad Mojahid Akhtar 👤 Member for 18 years 5 months

dear nike

go to right pan and click display and remove tick mark in "show all project".

than yoy will find in left pan display activity for selected become on. ok