Hi all,
I need to put a recurring activity in a schedule to show a meeting which is scheduled every 6 weeks. Is this possible in P6, if so, can anyone tell me how to do it please?
Many thanks.
Hi all,
I need to put a recurring activity in a schedule to show a meeting which is scheduled every 6 weeks. Is this possible in P6, if so, can anyone tell me how to do it please?
Many thanks.
Hi Jane
Set up a calendar that has one work day in a six week period of non work days and apply it to your "Meeting" task - the duration should be the number of anticipated meetings.
Make sure you add progress to block out the meetings as and when they occur.
Best regards
Mike Testro