What the difference b/w project baseline, primary, secondry & tertiary baseline programme ?

D
Deff Usman 👤 Member for 15 years 1 month

The Project baseline is your original reference for the project,Secondary will be the next reference and so on....

M
Mike Testro 👤 Member for 20 years 5 months

Hi Arun

The simple answer is how big is your software database?

Best regards

Mike Testro

A
Arun Kumar Singh 👤 Member for 14 years 8 months

HOw many activity we can use in a single project and what's the no of relationshipe we can assign in same programme.

means i have one programme in that 20000 nos activity with arround 60000 relationship

i want to know max no of activity and relationship in a single programme ??

D
Deff Usman 👤 Member for 15 years 1 month

It is the reference of your contract schedule,,,Thats you called the baseline schedule.

G
Gary Whitehead 👤 Member for 17 years 2 months

The project-level baseline is used for project/activity usage spreadsheets and profiles, as well as dates and earned value calculations 

The primary, secondary and tertiary are just for earned value and dates

R
Roland Payawan 👤 Member for 23 years

PORJECT BASELINE i may say is the first contractual approved master programme. Primary Baseline basically the Project Baseline or the approved revised programme. Secondary and Tertially baseline for me is the previous reporting period programme, that I used to  for easy monitoring which activities missed its previous reporting period target start and completion date.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts