What the difference b/w project baseline, primary, secondry & tertiary baseline programme ?
Project management
Forum Sponsor
Top Posters
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
The Project baseline is your original reference for the project,Secondary will be the next reference and so on....
Hi Arun
The simple answer is how big is your software database?
Best regards
Mike Testro
HOw many activity we can use in a single project and what's the no of relationshipe we can assign in same programme.
means i have one programme in that 20000 nos activity with arround 60000 relationship
i want to know max no of activity and relationship in a single programme ??
It is the reference of your contract schedule,,,Thats you called the baseline schedule.
The project-level baseline is used for project/activity usage spreadsheets and profiles, as well as dates and earned value calculations
The primary, secondary and tertiary are just for earned value and dates
PORJECT BASELINE i may say is the first contractual approved master programme. Primary Baseline basically the Project Baseline or the approved revised programme. Secondary and Tertially baseline for me is the previous reporting period programme, that I used to for easy monitoring which activities missed its previous reporting period target start and completion date.