FLoat Bars in Primavera P6

B
BRAVE G 👤 Member for 15 years 7 months

Completed activities are showing float bars tilll the project finish date. Is that right in p6.

 

 

Does anyone know this..

 

Thanks

B
BRAVE G 👤 Member for 15 years 7 months

You are starrrr. Thanks for reminding....

 

That is so rightttttttttttttttt....

 

 

Geofff

U
Utku Çil 👤 Member for 15 years

Geoff,

1. Right click on Gannt Chart

2. Select Bars

3. Change the filtering option for "Float Bar" from "All Activites" to "Not Started" & "In Progress"

 

I hope this helps.

Regards,

Utku.

B
BRAVE G 👤 Member for 15 years 7 months

Guys, 

 

 

Some of this activities have logic and have been completed and are still showing float bars extending to the project finish date.

 

 

A
Amit Parmar (PMP) 👤 Member for 15 years 6 months

Hi Geoff,

This happens if you are using "Retained Logic" as your scheduling option. Primavera needs to calculate Early and Late dates in case it has to calculate the dates for the Not Started Successor activities. If you use "Progress Override" or "Actual Dates" in scheduling options, Primavera will stop calculating Early and Late Dates for Completed activities. For more clarity on Scheduling Options, check this link at http://primaverablog.in/2011/07/scheduling-options-%e2%80%93-progressing-activities/

Simon- Even  open ended but Finished activities will not have float if you use Progress Override or Actual Dates in scheduling options

Regards

Amit

Check out my blog on Primavera at http://www.primaverablog.in

S
Simon Willson 👤 Member for 19 years 6 months

Hi Geoff,

If your tasks are open ended then they will have float until the end of the project.

Regards

Simon

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts