Milestones In The Wrong Place

Hi again!

This time I have milestones that are showing under activities that start on the same date as the milestone. How do I get the milestones above these activities???

Thanks,

Grace

A
Alaa Al haj 👤 Member for 18 years 7 months

hi Grace

did you try what Kumar suggest

i think this is the easiest way  

K
kumar s 👤 Member for 16 years 4 months

Grace..

One way you can do is sort the activities  by actiivity type in groups and sort.

 

Cheers

 

M
Mike Testro 👤 Member for 20 years 6 months

Hi Grace

In powerproject you just drag and drop milestones to wherever you want them to be.

This seems like another reason not to bother with P6.

Best regards

Mike Testro