Critical Path Change

A
AB Timo 👤 Member for 15 years

Hello All,

I have just come accross an issue that i never faced before.I have Planned a project and after finalizing the baseline when I updated it on the current data date,The critical path has transfered to Non.Critical.Now there is no critical activity in my Whole project.Anyone know the reason behind this??

G
Gary Whitehead 👤 Member for 17 years 3 months

Next most obvious thing to check is if there is a constraint at the project level.

Assuming you are using P6 (most do), you can check this from Enterprise > Projects. Right-click on your project from the EPS structure and select "Project Details". Go to the "Dates" tab and check that the "Must Finish By" field is blank

 

If it's not this, calendars would be the next thing I'd look at.

A
AB Timo 👤 Member for 15 years

Thanks Mike for The Reply.There is no constraint in my Schedule.I have checked all activities.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Faiz

There could be any number of reasons but the most common is that you have some Must End By constraints.

Remove ALL constraints and reschedule.

Best regards

MikeTestro

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts