Critical Path Change

A
AB Timo 👤 Member for 14 years 11 months

Hello All,

I have just come accross an issue that i never faced before.I have Planned a project and after finalizing the baseline when I updated it on the current data date,The critical path has transfered to Non.Critical.Now there is no critical activity in my Whole project.Anyone know the reason behind this??

G
Gary Whitehead 👤 Member for 17 years 2 months

Next most obvious thing to check is if there is a constraint at the project level.

Assuming you are using P6 (most do), you can check this from Enterprise > Projects. Right-click on your project from the EPS structure and select "Project Details". Go to the "Dates" tab and check that the "Must Finish By" field is blank

 

If it's not this, calendars would be the next thing I'd look at.

A
AB Timo 👤 Member for 14 years 11 months

Thanks Mike for The Reply.There is no constraint in my Schedule.I have checked all activities.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Faiz

There could be any number of reasons but the most common is that you have some Must End By constraints.

Remove ALL constraints and reschedule.

Best regards

MikeTestro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts