Total Float Bar on Completed Activities

U
Utku Çil 👤 Member for 15 years

Is there a way that I can remove the total float bar on completed activites?

I have an on-going schedule having completed, in progress & not started activities as can be predicted but I want to see the total float bar only for in progress & not started activities since, in my opinion, total float does not mean anything for completed activites.

Thanks in advance for who replies..

G
Gary Whitehead 👤 Member for 17 years 2 months

See extract from a Paul Harris presentation covering this:

 

[[wysiwyg_imageupload:675:]]