Earn Value Management
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Cost Variance (CV); CV=EV-CV>0, spending less than planned
Whereas;
Earned Value (EV) = Budgeted Cost of Work Performed (BCWP)
= Budget X Work Performed
Actual Cost (AC) = Actual Cost of Work Performed (ACWP)
= Actual Cost to Date
(Payment and Billing Status)
Schedule Variance (SV); SV=EV-PV>0, ahead of schedule
Whereas;
Earned Value (EV) = Budgeted Cost of Work Performed (BCWP)
= Budget X Work Performed
Planned Value (PV) = Budgeted Cost of Work Schedule (BCWS)
= Budget X Scheduled Work to Complete
[thread has been clarified]
What would you like to know