Adding Same Resource more than once

Hi

how are you guys.

I am facing one problem.

I want to assign same resource more than once in one activity.

e.g there are 20 Labors in one activity ( 100 dollar / day/ labor) . how to assign this 20 Labor to single activity.

Kindly help.

Planning_guy

A
AB Timo 👤 Member for 14 years 11 months

I think you are new in primavera.Follow this

No Adding process is different it is added in Remaining units/time

in this case..20*No of Hrz pr day and Write it in REmaining unit pr time

eg

20 Labors are working at 8 Hrz a day the 20*8=160

write 160 in Remaining hrz/day..Budgeted will be calculated auromatically

 

I think its clear now?

P
Planning guy 👤 Member for 14 years 11 months

Ya i know this is planned units , but where to input it in "Budgeted units"... in resource tabs...?

A
AB Timo 👤 Member for 14 years 11 months

No Thesee are Planned.Actual will be added after the activity Starts.

A
AB Timo 👤 Member for 14 years 11 months

First Add Resource in Resource window

Return to Activity Window and click on activity to which u want to assign resource.

Click on Resource Tab... and Assign..then right the unit (in your case 20*5=100)

A
AB Timo 👤 Member for 14 years 11 months

20 * No.of  days

 

For example,you have an activity where 20 labors will work for 5 days

20*5=100

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts