I am facing one problem.
I want to assign same resource more than once in one activity.
e.g there are 20 Labors in one activity ( 100 dollar / day/ labor) . how to assign this 20 Labor to single activity.
Kindly help.
Planning_guy
ya i am new thanks for sharing.........
I think you are new in primavera.Follow this
No Adding process is different it is added in Remaining units/time
in this case..20*No of Hrz pr day and Write it in REmaining unit pr time
eg
20 Labors are working at 8 Hrz a day the 20*8=160
write 160 in Remaining hrz/day..Budgeted will be calculated auromatically
I think its clear now?
Ya i know this is planned units , but where to input it in "Budgeted units"... in resource tabs...?
No Thesee are Planned.Actual will be added after the activity Starts.
Will it be the "Actual units" = 100 ...?/
First Add Resource in Resource window
Return to Activity Window and click on activity to which u want to assign resource.
Click on Resource Tab... and Assign..then right the unit (in your case 20*5=100)
how to input it in P6.??
20 * No.of days
For example,you have an activity where 20 labors will work for 5 days
20*5=100