Early and Late costs in Table Format

I can generate the resource cost curve using the Resource Usage Profile and get the graph that I want showing costs based upon early and late dates. How can I generate that same information in a tabular format on a month by month basis: costs by early and late dates?

A
Ayman Eleish 👤 Member for 15 years 6 months

Hi,

You can get it easly from "resource assignment windows",just copy and past to excell sheet.