Planning, Scheduling & Programming Discussion Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 09:34 Permalink RE: Updating P3 Programmes Thanks Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 09:28 Permalink RE: Updating P3 Programmes I think there is some mis-understanding. In P3 programme, on data structure, there are 2 levels, one is master and the other is sub (some user will name it project and sub-project). To make it simple, you need to review the activities (no matter in project or sub-project). Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 09:22 Permalink RE: Updating P3 Programmes When you say review the master,do I have to change anything in there. I thought the master and the Target are the same? Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 09:16 Permalink RE: Updating P3 Programmes Yes. Besides the sub-programmes, those activities in master level need to be review their progress also. Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 09:08 Permalink RE: Updating P3 Programmes So all I have to do is put the new dates in the sub progs and schedule to current date? Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 08:34 Permalink RE: Updating P3 Programmes Except the hommack, need to review all non-complete activites for progress input. I would like to name the process "progress input" or "progress update" rather "update" Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 08:27 Permalink RE: Updating P3 Programmes The Master has been devided into 3 sub programmes. I need to input new dates into the programmes to check progress or slipage. Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 07:51 Permalink RE: Updating P3 Programmes Mario, Would you mind to explain the meaning of update? Is it for input the progress or preparing a revision. The approach is different. Also you have mentioned the term master and sub of a P3 programme. P3 data structures need to be considered also. Member for 21 years 4 months Member for 21 years 5 months Submitted by Rajesh Moolakkandam on Sun, 2004-12-12 06:47 Permalink RE: Updating P3 Programmes Master program is not updated usually.you have to udate the current shedule only.Master program/base program is with which you are comparing the current progress. Log in or register to post comments
Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 09:34 Permalink RE: Updating P3 Programmes Thanks
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 09:28 Permalink RE: Updating P3 Programmes I think there is some mis-understanding. In P3 programme, on data structure, there are 2 levels, one is master and the other is sub (some user will name it project and sub-project). To make it simple, you need to review the activities (no matter in project or sub-project).
Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 09:22 Permalink RE: Updating P3 Programmes When you say review the master,do I have to change anything in there. I thought the master and the Target are the same?
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 09:16 Permalink RE: Updating P3 Programmes Yes. Besides the sub-programmes, those activities in master level need to be review their progress also.
Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 09:08 Permalink RE: Updating P3 Programmes So all I have to do is put the new dates in the sub progs and schedule to current date?
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 08:34 Permalink RE: Updating P3 Programmes Except the hommack, need to review all non-complete activites for progress input. I would like to name the process "progress input" or "progress update" rather "update"
Member for 21 years 6 months Member for 21 years 6 months Submitted by Mario Patel on Sun, 2004-12-12 08:27 Permalink RE: Updating P3 Programmes The Master has been devided into 3 sub programmes. I need to input new dates into the programmes to check progress or slipage.
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Sun, 2004-12-12 07:51 Permalink RE: Updating P3 Programmes Mario, Would you mind to explain the meaning of update? Is it for input the progress or preparing a revision. The approach is different. Also you have mentioned the term master and sub of a P3 programme. P3 data structures need to be considered also.
Member for 21 years 4 months Member for 21 years 5 months Submitted by Rajesh Moolakkandam on Sun, 2004-12-12 06:47 Permalink RE: Updating P3 Programmes Master program is not updated usually.you have to udate the current shedule only.Master program/base program is with which you are comparing the current progress.
Member for
21 years 6 monthsRE: Updating P3 Programmes
Thanks
Member for
23 years 8 monthsRE: Updating P3 Programmes
I think there is some mis-understanding.
In P3 programme, on data structure, there are 2 levels, one is master and the other is sub (some user will name it project and sub-project).
To make it simple, you need to review the activities (no matter in project or sub-project).
Member for
21 years 6 monthsRE: Updating P3 Programmes
When you say review the master,do I have to change anything in there. I thought the master and the Target are the same?
Member for
23 years 8 monthsRE: Updating P3 Programmes
Yes.
Besides the sub-programmes, those activities in master level need to be review their progress also.
Member for
21 years 6 monthsRE: Updating P3 Programmes
So all I have to do is put the new dates in the sub progs and schedule to current date?
Member for
23 years 8 monthsRE: Updating P3 Programmes
Except the hommack, need to review all non-complete activites for progress input.
I would like to name the process "progress input" or "progress update" rather "update"
Member for
21 years 6 monthsRE: Updating P3 Programmes
The Master has been devided into 3 sub programmes. I need to input new dates into the programmes to check progress or slipage.
Member for
23 years 8 monthsRE: Updating P3 Programmes
Mario,
Would you mind to explain the meaning of update?
Is it for input the progress or preparing a revision. The approach is different.
Also you have mentioned the term master and sub of a P3 programme. P3 data structures need to be considered also.
Member for
21 years 4 monthsRE: Updating P3 Programmes
Master program is not updated usually.you have to udate the current shedule only.Master program/base program is with which you are comparing the current progress.