Updating P3 Programmes

M
Mario Patel 👤 Member for 22 years 2 months
M
MK TSE 👤 Member for 24 years 4 months

I think there is some mis-understanding.

In P3 programme, on data structure, there are 2 levels, one is master and the other is sub (some user will name it project and sub-project).

To make it simple, you need to review the activities (no matter in project or sub-project).

M
Mario Patel 👤 Member for 22 years 2 months

When you say review the master,do I have to change anything in there. I thought the master and the Target are the same?

M
MK TSE 👤 Member for 24 years 4 months

Yes.

Besides the sub-programmes, those activities in master level need to be review their progress also.

M
Mario Patel 👤 Member for 22 years 2 months

So all I have to do is put the new dates in the sub progs and schedule to current date?

M
MK TSE 👤 Member for 24 years 4 months

Except the hommack, need to review all non-complete activites for progress input.

I would like to name the process "progress input" or "progress update" rather "update"

M
Mario Patel 👤 Member for 22 years 2 months

The Master has been devided into 3 sub programmes. I need to input new dates into the programmes to check progress or slipage.

M
MK TSE 👤 Member for 24 years 4 months

Mario,

Would you mind to explain the meaning of ’update’?

Is it for input the progress or preparing a revision. The approach is different.

Also you have mentioned the term ’master’ and ’sub’ of a P3 programme. P3 data structures need to be considered also.

R
Rajesh Moolakkandam 👤 Member for 22 years 1 month

Master program is not updated usually.you have to udate the current shedule only.Master program/base program is with which you are comparing the current progress.

Forum Sponsor

Top Posters

jaasland
0 posts
Doron El
3 posts
James Williams
74 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts