Hi Davidson,
Follow these steps:
1. Create new Activity Codes depending on your requirements.
2. Assign the group of activites in the newly added activity code.
3. When done, go to Bars --> Select Add & Rename, under Timescale "Remain Bar",
4. Under Filter, select New, under Parameter Where: Look for the activity code that you have assigned to each group of activities and make sure that you have mark the checkbox, select OK.
5. Change the Bar Style like Shape, Color, Pattern & Row then Apply.
Best regards,
Arnold
Sali ako dto....Mabuhay!!!
Dear Friends,
Did you know that you can also have your own forum discussion inside the Pinoy Planning Planet Community Group..
Join Group:
http://www.planningplanet.com/groups/500842/pinoy-planning-planet-commu…
Forum : (you need to join the above group to get to the forums)
http://www.planningplanet.com/groups/500842/pinoy-planning-planet-commu…
Hope this helps...PP Admin
Mga Kabayan,
This community is a great headstart para sa lahat ng Pinoy Planner/Schedulers. Sama-sama nating palakihin ang community!
Mabuhay tayong lahat!
Kabayan,
Ako po si Joseph Mangrobang, may dugong Tarlac pero laking Batangas. Bago lamang po ako sa Planning Community at marahil kakailanganin ang tulong ninyo. Matagal na ako sa Field construction at gumagamit na rin ng Primavera pero hanggang basic scheduling lang. Lately lang, I decided to make a career change at maging pokus sa planning. Napakaganda ng planning forum na ito at sa kung sino man ang nakaisip at nagsimula 'Maraming salamat po at Mabuhay kayo'.
Sa ngayon ay naghahanap po ako ng work which focuses on project planning and control. Do you know any company who are in need of a junior( I consider myself in this level) scheduler?
Davidson,
Yes it is possible, just play with "format bars" and "filters"
Hello Kabayan,
I have question which I can't do it in P6 v7 regarding the bar options, since our GM wants different colors on the bars to distinguish what he want to see but I cant change the color.
Could you please tell me if this is possible.
Thanks,
Mabuhay ang mga Filipino Planners...
Hello Mga KABABAYAN,
Musta kayong lahat mga Filipino Planners? Sa mga FILIPINO nating kasamahan sa buong mundo, ako po si Arnold. Anuman, ang kailangan ninyong tulong with regards to P6 v7 just email me sa [email protected] at sasagutin ko ito kung may time na ako.
Matagal na akong nagtuturo sa Primavera 6 version 7 at pwede ko kayong tulungan kapag free ako.
Maraming salamat po.
Mga kabayan,
P6 po pala ang Expertise ko.
Ako po ay tubong Cagayan Valley. Itawes, Ibanag, Ilokano na salita bukod po sa sariling atin.
Asahan po natin mga kabayan na dito po natin matatagpuan yung hinahanap natin na kapitbahay lang pero di naman po natin nakikita.
Regards to all.
Good day!!! as a new member, sana maging paki pakinabang ang forum na ito sa ating profession.It is very important for us to help each other. Any relevant contribution, suggestion and recommendation are most welcome to upgrade our knowledge in any industry.