There is some confusion going on ( I suppose). I have counted the No of Columns from the drawing and added this as a resource to Column activity in the program. Now the Program gives resource usage for the duration of activity. i want to know the no of columns which are to be cast on daily basis. which i have tried through the Report editor, but failed to do so.
If you are working on a high rise building, the columns will be dependent on the casting of the floors, why don't you just count directly from the drawings?
Member for
18 years 7 months
Member for18 years7 months
Submitted by Mangesh Khuspe on Thu, 2011-05-12 06:33
Member for
18 years 7 monthsDear Anoon, There is some
Dear Anoon,
There is some confusion going on ( I suppose). I have counted the No of Columns from the drawing and added this as a resource to Column activity in the program. Now the Program gives resource usage for the duration of activity. i want to know the no of columns which are to be cast on daily basis. which i have tried through the Report editor, but failed to do so.
I hope i am clear now.
Member for
19 years 1 monthIf you are working on a high
If you are working on a high rise building, the columns will be dependent on the casting of the floors, why don't you just count directly from the drawings?
Member for
18 years 7 monthsDear Anoon,Thanks for the
Dear Anoon,
Thanks for the reply, I didnt understand what you want to say. can you please explain?.
This is the simplest method for me as it will give the daily usage of resource.
Member for
19 years 1 monthyou can make your timescale
you can make your timescale on a daily basis, but I supposed your approach is wrong, it will depend on how you structure your activities