Hi All,
I have just taken over somebody elses plan for a framework agreement with lots of seperate jobs contained within. I am looking for the quickest way to move areas of the WBS into other areas. For example;
I am trying to move Job No 1 (Inc all descendants) from "On Hold" in WBS to "Ongoing" in WBS
What is the quickest way to do this? I normally use activity codes but there are 8,000 activities to update.
Kind Regards
Mike
Thanks Khalid, unfortunately I dont have P6 software on this laptop, thats why im stuck on P3. P6 makes it alot easier to transfer WBS as you have also demonstrated above.
Thanks Again
Mike
Hi Mike:
it will be helpfull to you if you import the program to p6.
im try to hepl you by my way of usiing p6 .
in p6 you can copy, cut and past the wbs with all asigned activities in any part you want , also inculding modification of activity code , p6 will ask you for renumbering of activities,
as follow:
[[wysiwyg_imageupload:464:]]