Start - Predecessor activity with a finish milestone

R
richu rose 👤 Member for 19 years 4 months
S
Shebin Thomas 👤 Member for 15 years 1 month

hi

Myself Shebin.

Regarding the same issue,is there any settings provided in P6 to change the default time for a finish milestone activity to commence at 6:00pm instead of 8:00 am. In my one project i changed the activity type of an activity from start milestone to finish milestone. The date then changed from 20-Mar-2011 07:00am to 20-Mar-2011 07:01 am. The same thing when i done in another project the time changed from 07:00am to 5:00 pm.Why this discrepancy? Can anyone help me in rectifying the issue please, then it would be greatly helpful.

Thank you

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Richu,



This problem has been corrected in P6 v7.



The only solution is to change the 8:01 into 8:00 AM



Regards,



Arnold

W
Wilfredo Jr. Flores 👤 Member for 20 years 9 months

Hi Richu,



What activity type did you assigned to Activity A.It should be finish Milestone with finish on constraint of 1Mar10. Then check the assigned calendar to your activities to correct the timings. As for Activity B, it will start using the same date and time of finish date of activity A



Regards

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts