Dear All,
Hi, I already have values in my custom defined field "WF". I cannot use global change so my Budget Labor Units will be equal to the values in my custom defined field "WF". Any work around?
Thank you.
Regards,
Num
Dear All,
Hi, I already have values in my custom defined field "WF". I cannot use global change so my Budget Labor Units will be equal to the values in my custom defined field "WF". Any work around?
Thank you.
Regards,
Num
Hi, anyone has solution for this one? Thanks.
Hi, anyone has solution for this one? Thanks.
Hi, I simply use 2 global change:
1. Global change 1 (Activities):
user_number6 = _sc wf
2. Global change 2 (Activity Resource Assignment):
Budgeted labor units = user_number6
Hi I already changed the security profiles but still it doesn't work.
Hi,
Can you please tell me what formula are you using while using global change.
Regards
Amit Parmar
Check out my blog on PrimaveraBlog at http://www.primaverablog.in
Hi Num Lock,
Please check your Security Profile assigned to you if you are not a superuser. You might not allowed to edit part or whole of the project data.
Hope this will help.
Regards,
Raymund