Same value of Budget Labor Units and Custom Defined Field using global change in P6

N
Num Lock 👤 Member for 19 years 7 months

Dear All,

Hi, I already have values in my custom defined field "WF". I cannot use global change so my Budget Labor Units will be equal to the values in my custom defined field "WF". Any work around? 

Thank you.

Regards,

Num

N
Num Lock 👤 Member for 19 years 7 months

Hi, I simply use 2 global change:

1. Global change 1 (Activities):

user_number6 = _sc wf

2. Global change 2 (Activity Resource Assignment):

Budgeted labor units = user_number6

N
Num Lock 👤 Member for 19 years 7 months

Hi I already changed the security profiles but still it doesn't work.

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi Num Lock,

Please check your Security Profile assigned to you if you are not a superuser. You might not allowed to edit part or whole of the project data.

 

Hope this will help.

 

Regards,

 

Raymund

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts