Hi
I want to create the project control room. here i want to know that what is sequence of activity.For example
1. Concept Note by Electrical department
2. assignment drawing to Civil & Structure, HVAC, Instrument
3. HVAC gives the assignment to CIVIL
and so on...
Can any one suggest the site where i can get son standard procedure or guide for sequencing to engineering project
Thanks in advanced
Regards'
KBJ
First need to summarize your bill of quantity for example , Circuit breakers etc to Distribution Board.Isolators ,Cables ,Cable Racks , Transformers , UPS, UPS DB Boards Etc. Now do the same for Instrumentation. On your Project file start with
Egg:
Utilities:
Cable Rack
Trunking
Power Equipment:
UPS
Generator
Field Equipment":
DB Boards
Isolators
Welding Plugs
Lightning and small power:
Plugs
Lights
Cables:
Small Power
LV Power
This is a very quick guide line
Winsted Worldwide Control Rooms
www.winsted.com Main (0) 1905 770276
Winsted Corporation has over 46 years experience in providing quality control room furniture solutions. Serving security, video, traffic, utility and defence control rooms world wide.
Winsted’s products, installation operations, and services are tailored specific to your requirements. Whether you need a single workstation, or a complete control room, we can provide the perfect solution. At Winsted we are pleased to offer you a Free design service to provide you with a clear vision of your console needs.
If you would like to discuss a project or require any additional information please do not hesitate to contact Darryl Lymer, Sales & Development Manager on telephone 07506 731 162, or at [email protected]
We look forward to hearing from you.
Yours sincerely
Stella Lewis
Marketing & Development
Many many Thanks GARY
In the next topic i want to know Compressor House Building Schdule.
Regards\\
KBJ
assuming the control room is to control new equipment, the design / procurement / construction sequence would be something like:
1) datasheets / specs for new equipment to be controlled
2) let orders for the same
3) vender details of the same back, including loading
4) spec for DCS / MCC / etc
5) let orders for the same
6) vender details of the same back, including sizing & ventilation requirements
7) HVAC design (if required)
8) Civils design
9) Civils construction to weatherproof
10) M&E installation
NB: This can be quite a length process as you have to design & order all your plant before you can start design on the control kit. If time is a factor, another option is to start HVAC and civils design & civils construction before the control kit is ordered, and over-engineer the solution to ensure it will be adequate (ie a bigger room than you think you'll need with more HVAC than you think you'll need). Obviously more expensive this way, but MCCs are often on the critical path of process projects so it can be worth it.
Dear Ali
Yes . i want to develop a new schedule for a control room (containing electrical, instrument panel, DCS Panel, electrical circuit breaker etc).
regard\\
KBJ
Kumar,
Little confused with your question. Are you going to develop a Schedule for new Control Room or what?
Please clarify.
Regards,
SE Ali