Hello,
i am new on this forum
i have to build a WBS for a construction project including design and procurement
i don't know exactly where to insert the shop drawing in my WBS, and how to develop the constrcution phase,
here is my proposition, if somebody can give me advice.... it will be great
regards
lolo
Generalities
Key Construction milestones
Facilities
Engineering
Design Development
IFC
Quantity Surveying
Tender package preparation
Procurement
Tendering
Tender Analysis
Tender Negotiation
Direct Purchase Order
Contract Award
Shop Drawing
Construction
Mobilization
Building 01
Substructure
Superstructure
Finishes
Furniture and Fittings
MEP
Lifts and Escalators
External Works
thank you all
my wbs evoluate since last time, and took care of your remarks
lolo
hi lolo,
as for as ur Generalities, Engineering & Procurement are concered it looks like ok.
but while applying wbs to your construction phase i think you should follow CSI Codes. which will be show like that :
I hope after follow these CSI codes it ill be help you in tracking & analyzing progress.
regards,,,,,
Check with your cost engineer and find out if there is a WBS for cost control, then match your schedule WBS with the cost WBS (cost accounts) as much as possible. You will be able to have solid KPIs for your project.
The cost engineer should be able to create / add any missing account(s) to match the schedule WBS.
I suggest For You To Put Shop Drawing in seperate Level ans contain sub levels Submission and Approva for exampll:
Shop Drawing
Shop Drawing Submission
Civil Shop Drawing.
Architectural Shop Drawing.
M.E.P Shop Drawing.
Landscape Shop Drawing
Shop Drawing Approval
Civil Shop Drawing.
Architectural Shop Drawing.
M.E.P Shop Drawing.
Landscape Shop Drawing
Hi,
I think you have placed the shop drawings at the right place. And that must have elements under it the submission of shop drawings – review / approval shop drawings – submission of material submittals – review / approval as well