example of Full Design and build construction project WBS

L
lolo choise 👤 Member for 15 years 2 months

Hello,

i am new on this forum

i have to build a WBS for a construction project including design and procurement

i don't know exactly where to insert the shop drawing in my WBS, and how to develop the constrcution phase,

here is my proposition, if somebody can give me advice....   it will be great

regards

lolo

 

Generalities

                Key Construction milestones

                Facilities

Engineering

                Design Development

                IFC

                Quantity Surveying

                Tender package preparation

                               

Procurement

                Tendering

                Tender Analysis

                Tender Negotiation

                Direct Purchase Order

                Contract Award

                Shop Drawing

Construction

                Mobilization

                Building 01

                                Substructure

                               Superstructure

                               Finishes

                               Furniture and Fittings

                               MEP

                               Lifts and Escalators

                               External Works

L
lolo choise 👤 Member for 15 years 2 months

thank you all

my wbs evoluate since last time, and took care of your remarks

lolo

I
Irfan Khan 👤 Member for 16 years 10 months

hi lolo,

 

as for as ur Generalities, Engineering & Procurement are concered it looks like ok.

but while applying wbs to your construction phase i think you should follow CSI Codes. which will be show like that :

  • Division 01 — General Requirements
  • Division 02 — Site Construction
  • Division 03 — Concrete
  • Division 04 — Masonry
  • Division 05 — Metals
  • Division 06 — Wood and Plastics
  • Division 07 — Thermal and Moisture Protection
  • Division 08 — Doors and Windows
  • Division 09 — Finishes
  • Division 10 — Specialties
  • Division 11 — Equipment
  • Division 12 — Furnishings
  • Division 13 — Special Construction
  • Division 14 — Conveying Systems
  • Division 15 — Mechanical
  • Division 16 — Electrical

 

I hope after follow these CSI codes it ill be help you in tracking & analyzing progress.

 

regards,,,,,

 

 

       

                     

N
Nelson A. Rodriguez 👤 Member for 18 years 2 months

Check with your cost engineer and find out if there is a WBS for cost control, then match your schedule WBS with the cost WBS (cost accounts) as much as possible. You will be able to have solid KPIs for your project.

The cost engineer should be able to create / add any missing account(s) to match the schedule WBS.   

A
Amro Ahmed 👤 Member for 17 years 5 months

I suggest For You To Put Shop Drawing in seperate Level ans contain sub levels Submission and Approva for exampll:

Shop Drawing

  Shop Drawing Submission

      Civil Shop Drawing.

      Architectural Shop Drawing.

      M.E.P Shop Drawing.

     Landscape Shop Drawing

  Shop Drawing Approval

       Civil Shop Drawing.

       Architectural Shop Drawing.

       M.E.P Shop Drawing.

      Landscape Shop Drawing 

T
Tanveer Ahmad Niazi 👤 Member for 20 years 5 months

Hi,

I think you have placed the shop drawings at the right place. And that must have elements under it the submission of shop drawings – review / approval shop drawings – submission of material submittals – review / approval as well

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts