Baseline dates are different after it incorporated to another schedule

Hi Planners,

                I am facing some problems in assigning Baseline to my current schedule. After completing the monthly progress updation on my current schedule, i copied it as a another project to use it as another baseline. But once i assigned this as new baseline schedule and assigned it as Project Baseline. But the dates are not same as the original.

If i view the baseline schedule alone, its showing different dates & if i incorporate it into another schedule it showing different dates. I don't know why it showing like this. Kindly help me to resolve this ASAP coz i've to submit the Schedule within 2 days.

 

Regards,

Krishna

K
Krishna Kumar 👤 Member for 19 years 4 months

Hi Friends,

                Thanks for your support to solve this issue. And i've got my dates by following Arnold suggestion as below,

 
User offline. Last seen 1 week 3 days ago. Offline
Joined: 2007-04-25
Content Credits: 1106
 
Add Contact-Network
Hi Rav,

Why do you want to update your Baseline?

Anyway, to update your Baseline, go to Project Menu --> Maintain Baseline --> Highlight the baseline & Select Update, Mark the “Update existing activities already in the baseline” & select Update Options, Mark the necessary checkboxes you need especially “Dates, duration and data date” then OK and UPDATE.

Notes: If you choose the ’Dates, durations, and data date’ option to ensure that these fields are updated, after you run the baseline update, you should restore the baseline project, then schedule and re-baseline the project.

HTH.

Arnold
 
So, finally it works & got the dates that i've required.
 
Regards,
Krishna
 
 
G
Gary Whitehead 👤 Member for 17 years 2 months

Open the baseline schedule, and run a global change to make planned dates = early/actual dates.

 

This should fix the problem.

K
Kumar Baiju 👤 Member for 15 years 4 months

Dear Krishna

          If you give some screen shot then it helps me to understand in better way.

 

Regards\\

K
Krishna Kumar 👤 Member for 19 years 4 months

Hi Raymund,

                   I have assigned it as Project Baseline & looking in Project Baseline start & finish. And one more thing that while preparing the baseline i have entered some actual dates but now after assigning it as baseline the dates are not same as the actual date that i have entered.

And i don't know that if anything wrong in the method of assigning the baseline, could you clarify me that after updating all the actuals if i want to save it as a baseline what is the exact procedure? Kindly clear me ASAP coz i have to submit in 2 days.

 

Regards,

Krishna

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

First, Check the Calendar if the default is the same as the Project activity calendars.

Second, I doubt maybe you are looking on the columns showing the Planned dates. Planned dates is different from the baseline dates.

To make sure of it, use the Gant bar to compare Current Schedule from Baseline Schedule.

Hope this will help.

 

regards,

 

Raymund

Forum Sponsor

Top Posters

bal aji
2 posts
Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts