Dear All,
Would you please advise me how to export Resource/Cost Assignment shown from Assignment menu on the Directory Bar?
Thanks
Tandyo
Dear All,
Would you please advise me how to export Resource/Cost Assignment shown from Assignment menu on the Directory Bar?
Thanks
Tandyo
Thanks a lot Arend.
I follow your guidance and it works.
Regards,
Tandyo
Tandyo,
You can also use the report wizzard to set up the fields over the time distribution you need and then output the report to a csv file.
Regards,
Arend.
Thanks All,
You are right. It works.
I tried on other machine (local database) and it works.
I work in the server database and can not work for such function.
Thanks
Tandyo W.
Hi,
You can try exporting data to an excel sheet, using the export function. You can design the template and set the data you want to export based on filters and columns
Regards
Amit Parmar
check out my blog on Primavera at http://www.primaverablog.in
Hi,
What all data do you want to export from Primavera?
Regards
Amit Parmar
Check out my blog on Primavera at http://www.primaverablog.in
Hi Tandyo,
I am using P6 and it works well by selecting, copy and paste. In the excel, I can see the loads in time intervals.[[wysiwyg_imageupload:272:]]
Thanks Raymund,
I already did, however it works only for resource description shown in the screen shot at upper left while it doesn't work for the resource assignment shown in upper right (resource assignment for every month/day)
Regards,
Tandyo
Hi,
Select Resources>>> Copy >>> Paste in excel.
Hope this will help.
Regards,
Raymund