Export Resource/Cost Assignment to Excel format.

Dear All,

 

Would you please advise me how to export Resource/Cost Assignment shown from Assignment menu on the Directory Bar?

 

 

Thanks

Tandyo

T
tandyo winarno 👤 Member for 16 years 10 months

Thanks a lot Arend.

I follow your guidance and it works.

 

 

Regards,
Tandyo

A
Arend Kok 👤 Member for 18 years

Tandyo,

 

You can also use the report wizzard to set up the fields over the time distribution you need and then output the report to a csv file.

 

Regards,

Arend.

T
tandyo winarno 👤 Member for 16 years 10 months

Thanks All,

 

You are right. It works.

I tried on other machine (local database) and it works.

I work in the server database and can not work for such function. 

 

Thanks

Tandyo W. 

A
Amit Parmar (PMP) 👤 Member for 15 years 6 months

Hi,

You can try exporting data to an excel sheet, using the export function. You can design the template and set the data you want to export based on filters and columns

Regards

Amit Parmar

check out my blog on Primavera at http://www.primaverablog.in

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi Tandyo,

I am using P6 and it works well by selecting, copy and paste. In the excel, I can see the loads in time intervals.[[wysiwyg_imageupload:272:]]

 

T
tandyo winarno 👤 Member for 16 years 10 months

Thanks Raymund,

I already did, however it works only for resource description shown in the screen shot at upper left while it doesn't work for the resource assignment shown in upper right (resource assignment for every month/day) 

 

 

Regards,

Tandyo

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

Select Resources>>> Copy >>> Paste in excel.

 

Hope this will help.

 

Regards,

 

Raymund

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts