Tracking

R
Rohit K 👤 Member for 18 years 1 month

Dear All,

I have created a schedule and the same has been approved by the clients. Now we want to monitor the progress based on this schedule. I have saved a copy of this original. Now the following steps were done by myself to track the progress: 

Tools - Tracking - Set Baseline (Baseline 1) ,for Entire Project . OK.

Then in the Gnatt Chart I introduced two columns for the Actual Start & Actual Finish along with Start and Finish of the approved schedule dates.

Then started to update the progress by entering the Actual starts and finishes for the activities, my dates in the Start and Finish also changes.

Not able to show the clients of the present condition.

Can anybody help me.

 

Thanks in advance for your help.

Rohit

R
Rohit K 👤 Member for 18 years 1 month

Dareen,

Thanks that was I looking for. I think now will work. If any thing else crops up will discuss it.

Rohit

T
Trevor Rabey 👤 Member for 20 years 6 months

"my dates in the Start and Finish also changes."

Of course they do.

Considering the start date, a task has either a planned start date (if it has not actually started), so that start = earliest start, or an actual start (if it has actually started), so that start = actual start.

Similarly, the finish date.

Switch to the Tracking Gantt view and the Tracking Table. Everything you need is there.

D
Darren Brown 👤 Member for 18 years 8 months

Rohit

 

Updating the actuals will override and overwrite the start and finish dates. Start and finish are live fields and will update to reflect the current bar dates. If you want to show against the planned dates then you need to show baseline start and finish columns.

 

Darren

K
Kumar Baiju 👤 Member for 15 years 3 months

Dear Danial

    i think you suggest for primavera. In MSP there task information in which there is three checking 1 plan 2. baseline 3. actual.

 

Regards\\

K
Kumar Baiju 👤 Member for 15 years 3 months

Dear Danial

      i am getting the same problem. after following your suggestion problem has been not solved

 

Regards\\

R
Rohit K 👤 Member for 18 years 1 month

Daniel,

There is no box to be checked for started to be highlighted in the Task Informatin box. Am using MSP2007. 

Rohit

D
Daniel Limson 👤 Member for 24 years 7 months

Rohit,

When updating actuals, open the Activity Details, click the activity you want to update  and then check the started box, input the actual start date and enter % complete on the Duration% and repeat for each activity. If the activity is already 100% complete checked finished box and enter actual finished date.

Regards,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts