Dareen,

Thanks that was I looking for. I think now will work. If any thing else crops up will discuss it.

Rohit

Member for

19 years 11 months

"my dates in the Start and Finish also changes."

Of course they do.

Considering the start date, a task has either a planned start date (if it has not actually started), so that start = earliest start, or an actual start (if it has actually started), so that start = actual start.

Similarly, the finish date.

Switch to the Tracking Gantt view and the Tracking Table. Everything you need is there.

Member for

18 years 2 months

Rohit

 

Updating the actuals will override and overwrite the start and finish dates. Start and finish are live fields and will update to reflect the current bar dates. If you want to show against the planned dates then you need to show baseline start and finish columns.

 

Darren

Member for

14 years 9 months

Dear Danial

    i think you suggest for primavera. In MSP there task information in which there is three checking 1 plan 2. baseline 3. actual.

 

Regards\\

Member for

14 years 9 months

Dear Danial

      i am getting the same problem. after following your suggestion problem has been not solved

 

Regards\\

Member for

17 years 6 months

Daniel,

There is no box to be checked for started to be highlighted in the Task Informatin box. Am using MSP2007. 

Rohit

Member for

24 years 1 month

Rohit,

When updating actuals, open the Activity Details, click the activity you want to update  and then check the started box, input the actual start date and enter % complete on the Duration% and repeat for each activity. If the activity is already 100% complete checked finished box and enter actual finished date.

Regards,

Daniel