What method to follow to save the data in the schedule(for eg: cost, budgeted quantities etc) while next updating of the schedule.
Thanks in advance.
Kannan
Hi,
What method to follow to save the data in the schedule(for eg: cost, budgeted quantities etc) while next updating of the schedule.
Thanks in advance.
Kannan
Hi Ronald,
Thanks a lot
Kannan
Kannan,