P3 data saving before new updating

K
Kannan CP 👤 Member for 18 years

Hi,

What method to follow to save the data in the schedule(for eg: cost, budgeted quantities etc) while next updating of the schedule.

Thanks in advance.

Kannan

R
Ronald Winter 👤 Member for 23 years 6 months

Kannan,

 

You should never modify your schedule once you published it.  Instead, you should make a complete copy of the schedule (under Tools / Project Utilities / Copy) and then update the copy.  Leave the old schedule untouched so that you can use it as a baseline.  Good luck!