Show time in minutes

Dear All,

Recently, i made an schedule for the our project but  i noticed that there an error in dates, it look like this.

Activity                 Duration          Start                                     Finish

Activity 1                  1          2 September 2010  11:00         3 September 2010  11:00

I have check already the calendar and other settings but the same nothing change. Calendar setting was 7:00 AM to 17:00 PM. The correct date should be 2 September 2010 07:00  - 2 September 2010 17:00

Please help me solve this problem.

 

Thanks,

Dan

S
Shareef Abdul Azeez 👤 Member for 20 years 8 months

Like what Rafael said check your ProjectStart date....don't forget to include minutes in your time format.

Another thing would be to check your data date (scheduled date & TIME)

Regards
Shareef A Aziz

S
Shareef Abdul Azeez 👤 Member for 20 years 8 months

Like what Rafael said check your ProjectStart date....don't forget to include minutes in your time format.

Another thing would be to check your data date (scheduled date & TIME)

Regards
Shareef A Aziz

R
Rafael Davila 👤 Member for 22 years 3 months

Did you verified project start date? It might be driving the start of the first activity and therefore the sucessors.

D
Dante Manito 👤 Member for 19 years 3 months

Hi Shajul,

 

Im using Primavera 6, I already check the working hours but the same nothing happen.

 

 

Regards,

 

Dante

S
Shah. HB 👤 Member for 17 years 6 months

Which software do you use ? I trust you need to check the working hours assigned in the calender 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts