Dear All,
Recently, i made an schedule for the our project but i noticed that there an error in dates, it look like this.
Activity Duration Start Finish
Activity 1 1 2 September 2010 11:00 3 September 2010 11:00
I have check already the calendar and other settings but the same nothing change. Calendar setting was 7:00 AM to 17:00 PM. The correct date should be 2 September 2010 07:00 - 2 September 2010 17:00
Please help me solve this problem.
Thanks,
Dan
Like what Rafael said check your ProjectStart date....don't forget to include minutes in your time format.
Another thing would be to check your data date (scheduled date & TIME)
Regards
Shareef A Aziz
Like what Rafael said check your ProjectStart date....don't forget to include minutes in your time format.
Another thing would be to check your data date (scheduled date & TIME)
Regards
Shareef A Aziz
Did you verified project start date? It might be driving the start of the first activity and therefore the sucessors.
Hi Shajul,
Im using Primavera 6, I already check the working hours but the same nothing happen.
Regards,
Dante
Which software do you use ? I trust you need to check the working hours assigned in the calender