Dear experts!
May I ask your help on what parameter to use in removing the performance % in each activity.
I tried the
If
Activity status is not equal to Not started
Then
Physical % = 0
But the % didnot change.
Hoping to share your knowledge on this matter.
Many Thanks
Chris
Simply deprogress by,
If
Physical % Complete is within range of 1% and 100%
Then
Physical % Complete = 0%
Duration % Complete = 0%
Actual Start =
Actual Finish =
Thank you Roger for the detailed information you had given to me. My programme was reset already.
1. Choose 'Enterprise', 'Projects' and select the calculations tab. Choose 'Link budget and at completion for not started activities' and 'Reset remaining duration and units to original'
2. Choose view,columns and add the columns for 'Actual labor units' and 'Actual non labor units'
3. Choose tools, schedule and set the data date equal to the project start date and schedule. To find the project start date, choose Enterprise, Projects. click on the dates tab and note the planned start date.
4. For the first activity in the list, set the actual labor units to zero. Highlight the activities in this column and choose edit, fill down
5. Do the same for the actual non labor units
6. Global changes then required
Subject area - Activity Resource Assignments
Where Resource Type = Material
Then Actual Material units = 0
Subject area - Activities
Where activity status is not equal to not started
Then activity status = Not started
Subject area - Activities
Where activity status = Not started
Then Remaining duration = Original duration
Everything in the project is now not started and reset to original programme
Regards
Roger