Dear Dean,
I recommend that you divide the project into:
Main Building
Annexes; Sewage Treatment Plant, Water Treament Plant
Landscape Works.
The Main Building is the Critical of course. I assume that you have several basements. Once you finish you 2nd basement from the bottom, your 1st basement formwork will be removed, and you can start your EM activities. The EM activities in the public areas will stay up to the end. Usually you have the space open for rent and the Tenants will do the EM works themselves. All you have to do is bring the networks up to their connection points.
EM Activities can goin parallel, but usuall you have:
1. HVAC works; marking, support system, ducting, testing, insulation.
2. Fire Fighting works: marking, support system, ducting, testing, insulation.
3. Plumbing
4. LPG
Electrial works must start with the Cable Trays, then you install the main cables and at last you do the termination of the Main Electrical Panels (Power, lightin, low current).
Once you complete the Main Building structure, you can start with the Facade works.
The bounday walls you can start at your earliest. It will give you site security and you will save up on the fencing.
The people movers (escalators, etc) are long lead items. So you must get approval and order them within max 3 months period.
The signage will not be clear until the mall is rented out and that is at the last stages.
Hope that the information helps.
With kind regards,
Samer
Thanks for all the replies.
here is my set of activities, which has to be completed in around 24 months time.
Civil work (Structure) 12 months
Building finishes 12 months
Facade- Glazing
Cornices external finishes
Landscapping
External works like Boundary walls and roads
Plumbing
Signage
Car parking management system
Gas bank
Public address system
Escalators & lifts.
Electrical
Firefighting
Sewage Treat Plant
Water Treat Plant
DG sets
HSD tanks for DG
AC includes
Access control system
CCTV
BMS
lighting arrangement inside and external lighting.
Can someone guide me which MEP activity can go parallel and with what activity.
what kinda relationship that can be established from the given set of details.
kindly guide me.
Before you start open up the project estimate, get an idea what there CBS is ..map there CBS to project WBS and the details that Samer has provided.
It will give you most of the details that you are looking for..including details for resource loading the schedule. Thanks.
Dear Dean,
How about if we write it up here. It will take up 1-2 days from your time.
The is level 1:
Excavation
Skeleton Works and E/M first fix
Electromechanical Works
Finishing Works
Cladding
Fit up period for tenants.
Kitchens
Toilets
Elevators and Escalators and people movers
Metal Works
Wood Works
Water features
Landscaping
Signage
Give us a bit more idea about your project, and we can give you more details about what is needed to be accomplished. This will enable you to complete your Program in no time.
With kind regards,
Samer
Hi
In addition to Samers post ,add WBS for Testing & Commissioning